Pre-Application Review: Wekiva Wastewater Treatment Plant Improvements

Original title: 9:20 AM (TEAMS) WEKIVA WWTP - PRE-APPLICATION Project Number: 26-80000060 Project Description: Proposed Site Plan for site improvements at an existing wastewater treatment plant on 38.68 acres in the PD zoning district located on the north side of Wekiva Trl, east of Ledbury Dr Project Manager: Kaitlyn Apgar (407) 665-7377 (kapgar@seminolecountyfl.gov) Parcel ID: 05-21-29-300-001B-0000 BCC District: 3-Constantine Applicant: Sean Twomey (866) 842-8432 Consultant: Jeff Pena (407) 487-2594

June 24, 2026

Track this bill to get notified when it advances a stage. One tap to stop, anytime.

Finance Connection

Notable money activity
$9,570across 19 reported contributions
Trace money trail →
CandidateDonorAmountIndustryDate
Constantine for Mayor 2020Plumbers, Pipefitters UA Local 393$1,000-Aug 2020
Constantine for Mayor 2020International Association of Fire Fighters$1,000-Jul 2021
Constantine for Mayor 2020International Association of Fire Fighters$1,000-Oct 2020
Constantine for Mayor 2020International Association of Fire Fighters$1,000-Oct 2020
Constantine for Mayor 2020International Association of Fire Fighters$1,000-Oct 2020
Constantine for Mayor 2020Cal Fire Local 2881 - Small Contributor PAC #790318$1,000-Jun 2021
Constantine for Mayor 2020International Brotherhoods of Electrical WorkersLocal Union 332$750-Aug 2020
Constantine for Mayor 2020Nora Campos$500ConsultantOct 2021
Constantine for Mayor 2020Rick Callender$500Manager of Government RelationsAug 2021
Constantine for Mayor 2020Dana Ditmore$350Business ConsultantOct 2021
Constantine for Mayor 2020Northern California Carpenters Regional Council$300-Sep 2020
David Constantine for City Council 2022Chris Staples$250ITMar 2022
David Constantine for City Council 2022Max Ordonez$233PresidentApr 2022
David Constantine for City Council 2022Marci Sanchez$187CounselorMar 2022
David Constantine for City Council 2022Jacque Priest$100unknownMay 2022
Constantine for Mayor 2022Judith Rickard$100RetiredAug 2022
David Constantine for City Council 2022Norma Amezcua$100Program ManagerMar 2022
David Constantine for City Council 2022Ana Radillo$100UNKNOWNMay 2022
Constantine for Mayor 2022Judith Rickard$100RetiredAug 2022

Reported financial relationships and timing signals. This does not prove motive or influence. Readers draw their own conclusions.

The Frame

What this does

The project involves site improvements to a wastewater treatment facility located on 38.68 acres, which may impact local utility infrastructure and land use in District 3.

Who is mentioned in the record

Potentially affected actors named in the source documents. Mention is not a position.

Residents of District 3

The project involves infrastructure improvements within their district.

Development Review Committee

The committee is responsible for reviewing the proposed site plan.

What changed

Last recorded activity June 24, 2026.

What's next

Next step not available in the current record.

Summary

This document outlines a meeting for proposed site improvements at the existing Wekiva wastewater treatment plant. The project is scheduled for review by the Development Review Committee on June 9, 2026.

Key Facts

  • The project involves site improvements at an existing wastewater treatment plant.
  • The site covers 38.68 acres.
  • The property is located in the PD (Planned Development) zoning district.
  • The site is situated on the north side of Wekiva Trl, east of Ledbury Dr.
  • The project is identified by number 26-80000060.
  • The review is scheduled for June 9, 2026, at 9:20 AM via TEAMS.
  • The project is located in BCC District 3.
  • The Parcel ID for the site is 05-21-29-300-001B-0000.

Frequently Asked Questions

What is a pre-application meeting?
It is an initial meeting where developers discuss proposed site plans with the Development Review Committee before formally submitting an application.
How can I contact the project manager?
You can contact Kaitlyn Apgar at (407) 665-7377 or via email at kapgar@seminolecountyfl.gov.

Why It Matters

The project involves site improvements to a wastewater treatment facility located on 38.68 acres, which may impact local utility infrastructure and land use in District 3.

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Sponsors

Connected Entities

personSean TwomeyApplicantMap →
other26-80000060Project NumberMap →
locationWekiva TrlLocation of the project siteMap →
personJeff PenaConsultantMap →
personConstantineBCC District 3 CommissionerMap →
personKaitlyn ApgarProject Manager for Seminole CountyMap →

Sources

Open source document

webapi.legistar.com

Analysis Score

0–100
  • Significance30
    How much this matters to a regular citizen
  • Controversy10
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz10
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record