ALACHUA (ALACHUA COUNTY) · LOCALlocal legislationAgenda Ready
Local Impact

Project Update: Cuscowilla Nature and Retreat Center

Original title: BBI Change Order and Deadline Extension for the Cuscowilla Nature and Retreat Center Project

January 24, 2023

Track this bill to get notified when it advances a stage. One tap to stop, anytime.

The Frame

What this does

The project timeline and contract terms for the Cuscowilla Nature and Retreat Center are being modified, which impacts the completion date and potentially the total cost of the county-funded facility.

Who is mentioned in the record

Potentially affected actors named in the source documents. Mention is not a position.

Board of County Commissioners

The board must vote to approve or deny the requested changes to the project contract.

County Residents

Residents are affected by the adjusted completion date and potential changes to the project budget funded by public resources.

What changed

Last recorded activity January 24, 2023.

What's next

Next step not available in the current record.

Summary

This document is a for the Board of County Commissioners regarding a and deadline extension for the Cuscowilla Nature and Retreat Center construction project.

Key Facts

  • The document is filed under reference number 23-0298.
  • The item is classified as a 'Consent Item', typically indicating it is expected to pass without extensive debate.
  • The action involves a formal change order for the Cuscowilla Nature and Retreat Center project.
  • The action includes an extension of the project deadline.
  • The item was introduced to the Board of County Commissioners on January 3, 2023.

Frequently Asked Questions

What is a 'Consent Item'?
A is a procedural designation for agenda items that are considered routine or non-controversial and are typically approved in a single vote without individual discussion.
What is a 'Change Order'?
A is a formal document used to modify the original scope, cost, or timeline of a construction contract.

Why It Matters

The project timeline and contract terms for the Cuscowilla Nature and Retreat Center are being modified, which impacts the completion date and potentially the total cost of the county-funded facility.

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Discoveries

Patterns POLISCOPE noticed across the record. These are observations to investigate, not conclusions.

policy shift70% confidence

Project Delay Pattern

The filing of a change order and deadline extension suggests the project is not meeting its original construction schedule.

Connected Entities

locationCuscowilla Nature and Retreat CenterThe specific facility undergoing construction and timeline adjustments.Map →
organizationBoard of County CommissionersThe governing body reviewing and approving the project changes.Map →

Sources

Open source document

webapi.legistar.com

Analysis Score

0–100
  • Significance40
    How much this matters to a regular citizen
  • Controversy10
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz10
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record