Passed

Approval of Boland Drive Drainage Improvement Project

Original title: Approve and authorize Staff to proceed with the construction of the Boland Drive Drainage Improvement Project in accordance with County Manager Policy #82 - Non-Board Approved Projects; approve and authorize the Chairman to execute a Resolution implementing Budget Amendment Request (BAR) #25-049 in the 2014 Infrastructure Sales Tax Fund to appropriate funding in the amount of $847,704.00. District1 - Dallari (John Slot, Public Works Director)

July 22, 2025

Track this bill to get notified when it advances a stage. One tap to stop, anytime.

The Frame

What this does

This project authorizes $847,704 in public funds for drainage construction in District 1, which will be managed under existing county policy for non-board approved projects.

Who is mentioned in the record

Potentially affected actors named in the source documents. Mention is not a position.

District 1 residents

Residents in this district will see construction activity related to the Boland Drive drainage improvements.

Public Works Department

Staff are authorized to proceed with the construction and management of the project.

What changed

Last recorded activity July 22, 2025.

What's next

Next step not available in the current record.

Summary

The Board of County Commissioners has approved the construction of a drainage improvement project on Boland Drive. The project is funded by an $847,704 budget amendment to the 2014 Infrastructure Sales Tax Fund.

Key Facts

You don't have to trust us. Each fact below is taken straight from the official document - click any one to see the exact passage, highlighted in the original.

Frequently Asked Questions

How is the Boland Drive project being funded?
The project is funded by an $847,704 appropriation from the 2014 Infrastructure Sales Tax Fund via Budget Amendment Request #25-049.
What is the purpose of this project?
The project is for drainage improvements on Boland Drive.

Why It Matters

This project authorizes $847,704 in public funds for drainage construction in District 1, which will be managed under existing county policy for non-board approved projects.

News Coverage

No news coverage found yet. Articles are indexed twice daily.

Sponsors

Discoveries

Patterns POLISCOPE noticed across the record. These are observations to investigate, not conclusions.

policy shift90% confidence

Use of Non-Board Approved Policy

The project is being executed under County Manager Policy #82, which allows for construction to proceed without individual board approval for each phase.

Connected Entities

Sources

Open source document

webapi.legistar.com

Analysis Score

0–100
  • Significance45
    How much this matters to a regular citizen
  • Controversy10
    Intensity of disagreement among stakeholders
  • Entertainment5
    Compellingness for a non-policy-wonk reader
  • Buzz15
    Current news / social attention level

Publisher tools

Share or embed this record

POLISCOPE publisher tools

Share or embed this record